From Jun 7-8, 2014, this LB1500 asphalt mixing plant final user came to inspected his plant. Following with our checklist, they tested every parts of the plant in detail. They satisfied this LB1500 very much and asked us arrange the delivery ASAP.
From Jun 12-13, we start to transport this LB1500 asphalt mixing plant and dispatch one of our staff go to Shanghai port to supervise the plants into container. The ship will leave China on Jun 19.
We re-designed this LB1500 under the situation of Thailand, considering the ground condition in Thailand we modified our drawing paper and the plant’s support legs. We design the electrical heating bitumen system for them as their government requirement. As customer’s project opening date is near, we manufactured this plant with high quality in a very short one month. Final customer thought we are truly solved their problems and speak highly of us.
When the LB1500 arrive at Thailand, we will pick up professional engineers to guide them install the plant and training their workers for operate.